The PDCA (Plan-Do-Check-Act) cycle is a core principle of ISO 45001 and many other management systems. It does not include environmental management, as ISO 45001 focuses on Occupational Health & Safety (OH&S), while environmental aspects are covered by ISO 14001.
Analysis of Options:
A. Treatment of Risks:Correct. Risk assessment and control are part of the Plan phase.
B. OHSMS Policy:Correct. The OH&S policy is established in the Plan phase.
C. Environment Management Program:Incorrect. This is outside the scope of ISO 45001 and pertains to ISO 14001.
D. Analyzing OHSMS Performance:Correct. Performance analysis occurs in the Check phase of the PDCA cycle.
ISO Reference:
Clause 0.3: PDCA model in ISO 45001.