TheTasksdashboard in Prism Element provides detailed visibility into the progress of all ongoing and completed tasks, including Life Cycle Manager (LCM) updates. Administrators can monitor the step-by-step status of LCM operations, track failures, and identify bottlenecks.
A. Analysis:Incorrect, as this is used for performance monitoring, not task progress.
B. Tasks:Correct, as it displays detailed progress for updates and other operations.
C. Hardware:Incorrect, as this focuses on the state and configuration of hardware components.
D. Alerts:Incorrect, as this shows system alerts and issues, not detailed task progress.
[References:, Nutanix Life Cycle Manager Guide: Monitoring Updates., Prism Element Administration Guide: Tasks Dashboard., ]