Program requirements for a hospital with a clear span of 70 feet include minimal disruption of the hospital routine for future mechanical and electrical repairs and alterations and a maximum economical flexibility of the structure.

Which of the following structural systems is most appropriate?


A.

Interstitial trusses


B.

Plate girders


C.

Composite floor beams


D.

Precast concrete planks