NCARB ARE 5.0 Project Planning & Design (PPD) Project-Planning-Design Question # 22 Topic 3 Discussion

NCARB ARE 5.0 Project Planning & Design (PPD) Project-Planning-Design Question # 22 Topic 3 Discussion

Project-Planning-Design Exam Topic 3 Question 22 Discussion:
Question #: 22
Topic #: 3

Which of the following is the most appropriate action for the architect to take in preparing a construction cost estimate for an owner after completing the schematic design phase?


A.

Include a larger contingency percentage for the design development phase than for the construction document phase.


B.

Vary the amount of the contingency allowance depending on the funds in the possession of the owner.


C.

Provide the greatest contingency allowance in the construction administration phase.


D.

Double the contingency allowance for profit if the owner requires the use of a construction manager.


Get Premium Project-Planning-Design Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.