Question #: 59
Topic #: 6

An IT integration delivery team begins a project by gathering all of the requirements, and proceeds to execute the remaining project activities as sequential, non-repeating phases.

Which IT project delivery methodology is this team following?


A.

Kanban


B.

Scrum


C.

Waterfall


D.

Agile