ITIL 4 Specialist: Business Relationship Management ITIL-4-BRM Question # 6 Topic 1 Discussion

ITIL 4 Specialist: Business Relationship Management ITIL-4-BRM Question # 6 Topic 1 Discussion

ITIL-4-BRM Exam Topic 1 Question 6 Discussion:
Question #: 6
Topic #: 1

Which is an example of the ‘Prepare the team’ step of Gemba walks?


A.

A business relationship manager informs staff of a future Gemba walk of the value stream for creating a new service


B.

A relationship manager records the findings of observing the negotiation of service targets


C.

A relationship manager asks another manager to join the Gemba walk for onboarding new customers


D.

A relationship manager discusses the findings of a Gemba walk with other stakeholders


Get Premium ITIL-4-BRM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.