Your team has been working on an Agile project for two months. There is a retrospective at the endof each sprint One of the data items reviewed is how many defects are being caught by users rather than by testers. The test team is being blamed for these escapes

What do you need to do to make these sessions more productive?


A.

You should attend the retrospective instead of the individual testers


B.

You should do root cause analysis to prove the developers are responsible


C.

You should gather metrics to present to the team regarding all the hours spent testing


D.

You should help the team brainstorm ideas on how to improve the testing to eliminate the escapes