ISTQB Certified Tester Advanced Level Test Management (CTAL-TM) v3.0 CTAL-TM Question # 27 Topic 3 Discussion

ISTQB Certified Tester Advanced Level Test Management (CTAL-TM) v3.0 CTAL-TM Question # 27 Topic 3 Discussion

CTAL-TM Exam Topic 3 Question 27 Discussion:
Question #: 27
Topic #: 3

SCENARIO 1

DreamPartner dating agency are redesigning their dating application following a major security breach in which sensitive customer data was made publically available. The redesign includes stronger security encryption and performance tuning.

The product risk register for the redesign project, which was produced after all requirements had been agreed, includes the following:

CTAL-TM Question 27

The organisational Test Strategy contains the following objectives:

1. A Risk-based lest approach must be adopted for all projects

2. Functional regression testing should start as soon as functional testing is complete

3. Automated tests may be run before or in parallel with manual tests

The project Test Plan has allocated 6 weeks to complete all test execution, with functional testing taking 3 weeks to execute, performance and security testing 2 weeks each and regression testing 1 week.

Which of the following options places the test suites (TS1 to TS5) in the correct order for test execution?

SELECT ONE OPTION


A.

TS3, TS1, TS2, TS5, TS4.


B.

TS1, TS2, TS5, TS3, TS4.


C.

TS3, TS4, TS1, TS2, TS5.


D.

TS5, TR1, TS3 TSA, TS2


Get Premium CTAL-TM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.