CTAL-TM Exam Topic 2 Question 10 Discussion:
Question #: 10
Topic #: 2

You are writing a system test level plan and are defining the test activities that must take place during test implementation. There is an established project risk register in place, with product risks addressing all new features to be developed. Three time-boxed cycles of system test execution are planned, and all the new features will be delivered in the first cycle.

The project test strategy states that the stakeholders require an overall view of the product quality for these features. This should be achieved by planning to test each product risk, to some degree, during the first cycle of test execution.

Which risk-based mitigation approach should be adopted during test implementation, to BEST meet the stakeholders' requirement?


A.

Cost of exposure analysis


B.

FMEA


C.

Depth-first test scheduling


D.

Breadth-first test scheduling