ISTQB Certified Tester Advanced Level Test Management (CTAL-TM) v3.0 CTAL-TM Question # 7 Topic 1 Discussion

ISTQB Certified Tester Advanced Level Test Management (CTAL-TM) v3.0 CTAL-TM Question # 7 Topic 1 Discussion

CTAL-TM Exam Topic 1 Question 7 Discussion:
Question #: 7
Topic #: 1

You are writing the project test plan and are analysing the following risks in the project risk register:

CTAL-TM Question 7

Which would be the MOST appropriate test activities to mitigate the product risks?


A.

Ignore Risk 1 as this cannot be mitigated by testing activities. Apply performance testing for Risk 2 and schedule it ahead of security testing for Risk 4. Disregard Risk 3 as it cannot be mitigated by test activities


B.

Apply portability testing for Risk 1 and schedule it ahead of security testing for Risk 4 and finally performance testing for Risk 2. Embed users with visual disabilities into the design team for Risk 3


C.

Ignore Risk 1 as this cannot be mitigated by testing activities. Apply security testing for Risk 4 and schedule it ahead of performance testing for Risk 2. Conduct reviews of early screen designs and involve users with visual disabilities


D.

Ignore Risk 1 as this is not within scope of a project test strategy. Apply performance testing for Risks 2 and 4, but schedule Risk 4 testing first. Ensure end-users with visual disabilities are involved during UAT