ISTQB Certified Tester Advanced Level Test Management (CTAL-TM) v3.0 CTAL-TM Question # 1 Topic 1 Discussion

ISTQB Certified Tester Advanced Level Test Management (CTAL-TM) v3.0 CTAL-TM Question # 1 Topic 1 Discussion

CTAL-TM Exam Topic 1 Question 1 Discussion:
Question #: 1
Topic #: 1

Consider the following metrics:

a Percentage of all product risks identified during initial risk analysis

b. Average time taken by developers to fix defects for each severity level

c. Statement coverage achieved by the component test suite

d. Breakdown of defects detected by test level

How many of the five primary dimensions for test progress monitoring have been addressed by these metrics?

SELECT ONE OPTION


A.

2


B.

4


C.

1


D.

3