For each of the test cases to be executed, the following table specifies the priority order and dependencies on other test cases

CTFL_Syll_4.0 Question 35

Which of the following test execution schedules is compatible with the logical dependencies and allows executing the test cases in priority order?


A.

TC4, TC3, TC2, TC6, TC5. TC1


B.

TC4, TC6, TC3, TC2, TC5, TC1


C.

TC3, TC5, TC6, TC1, TC4, TC3


D.

TC4, TC3, TC2, TC6, TC1, TC5