iSQI ISTQB® Certified Tester Advanced Level - Test Manager [Syllabus 2012] CTAL-TM_Syll2012 Question # 17 Topic 2 Discussion

iSQI ISTQB® Certified Tester Advanced Level - Test Manager [Syllabus 2012] CTAL-TM_Syll2012 Question # 17 Topic 2 Discussion

CTAL-TM_Syll2012 Exam Topic 2 Question 17 Discussion:
Question #: 17
Topic #: 2

You are the Test Manager on a new project. The schedule is aggressive and will require the team to work at peak efficiency. The requirements are not well defined yet, but it is clear that the

project will be using new technologies. To help the developers meet the development schedule, an offshore group will be added to the development team.

At this time there is not enough budget to add more testing resources. The project stakeholders are very concerned about the quality of delivered product and will be watching the project closely,

particularly during the testing cycles. The exit criteria from the system test level require no open high priority/severity defects, 100% pass rate for all test cases covering risks that are classified as

"high" or "very high", 90% pass rate for all "medium" risks and 50% pass rate for all "low" and "very low" risks.

Given this information, which lifecycle model should you recommend?[3]


A.

Spiral


B.

Iterative/incremental


C.

V-model


D.

Waterfall