Question #: 15
Topic #: 2

You are not confident with the assessment of the risk level and you suspect that it will be possible to find high-priority bugs in low-risk areas.

Furthermore the period for test execution is very short. Your goal is to test all the product risks in a risk-based way, while assuring that each product risk gets at least some amount of testing.

CTAL-TM_Syll2012 Question 15

Which of the following answers describes the best test execution schedule in this scenario?

Number of correct responses: 1

K32 credits


A.

T1, T2, T3, T4, T5, T6, T7, T8, T9, T10


B.

T1, T3, T5, T7, T9, T2, T4, T6, T8, T10


C.

T10, T9, T8, T7, T6, T5, T4, T3, T2, T1


D.

T10, T8, T6, T4, T2, T9, T7, T5, T3, T1