ISC ISSMP®: Information Systems Security Management Professional ISSMP Question # 21 Topic 3 Discussion
ISSMP Exam Topic 3 Question 21 Discussion:
Question #: 21
Topic #: 3
Mark is the project manager of the NHQ project in Spartech Inc. The project has an asset valued at $195,000 and is subjected to an exposure factor of 35 percent. What will be the Single Loss Expectancy of the project?