ISSMP Exam Topic 3 Question 21 Discussion:
Question #: 21
Topic #: 3

Mark is the project manager of the NHQ project in Spartech Inc. The project has an asset valued at $195,000 and is subjected to an exposure factor of 35 percent. What will be the Single Loss Expectancy of the project?


A.

$92,600


B.

$67,250


C.

$68,250


D.

$72,650