You and your project team have identified the project risks and now are analyzing the probability and impact of the risks. What type of analysis of the risks provides a quick and high-level review of each identified risk event?


A.

Quantitative risk analysis


B.

Qualitative risk analysis


C.

Seven risk responses


D.

A risk probability-impact matrix