Question #: 13
Topic #: 2

You work as a project manager for BlueWell Inc. You with your team are using a method or a (technical) process that conceives the risks even if all theoretically possible safety measures would be applied. One of your team member wants to know that what is a residual risk. What will you reply to your team member?


A.

It is a risk that remains because no risk response is taken.


B.

It is a risk that can not be addressed by a risk response.


C.

It is a risk that will remain no matter what type of risk response is offered.


D.

It is a risk that remains after planned risk responses are taken.


Get Premium CSSLP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.