Question #: 478
Topic #: 48

A vendor's planned maintenance schedule will cause a critical application to temporarily lose failover capabilities. Of the following, who should approve this proposed schedule?


A.

Business continuity manager


B.

Chief risk officer (CRO)


C.

IT infrastructure manager


D.

Business application owner