Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

Isaca Certified in Risk and Information Systems Control CRISC Question # 174 Topic 18 Discussion

Isaca Certified in Risk and Information Systems Control CRISC Question # 174 Topic 18 Discussion

CRISC Exam Topic 18 Question 174 Discussion:
Question #: 174
Topic #: 18

The PRIMARY benefit of selecting an appropriate set of key risk indicators (KRIs) is that they:


A.

serve as a basis for measuring risk appetite.


B.

align with the organization ' s risk profile.


C.

provide a warning of emerging high-risk conditions.


D.

provide data for updating the risk register.


Get Premium CRISC Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.