Isaca Certified in Risk and Information Systems Control CRISC Question # 471 Topic 48 Discussion

Isaca Certified in Risk and Information Systems Control CRISC Question # 471 Topic 48 Discussion

CRISC Exam Topic 48 Question 471 Discussion:
Question #: 471
Topic #: 48

Which of the following is the PRIMARY reason to update a risk register with risk assessment results?


A.

To communicate the level and priority of assessed risk to management


B.

To provide a comprehensive inventory of risk across the organization


C.

To assign a risk owner to manage the risk


D.

To enable the creation of action plans to address nsk