A business unit is updating a risk register with assessment results for a key project. Which of the following is MOST important to capture in the register?


A.

The methodology used to perform the risk assessment


B.

Action plans to address risk scenarios requiring treatment


C.

Date and status of the last project milestone


D.

The individuals assigned ownership of controls