Question #: 393
Topic #: 40

Which of the following is the PRIMARY advantage of having a single integrated business continuity plan (BCP) rather than each business unit developing its own BCP?


A.

It provides assurance of timely business process response and effectiveness.


B.

It supports effective use of resources and provides reasonable confidence of recoverability.


C.

It enables effective BCP maintenance and updates to reflect organizational changes.


D.

It decreases the risk of downtime and operational losses in the event of a disruption.


Get Premium CRISC Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.