Isaca Certified in Risk and Information Systems Control CRISC Question # 22 Topic 3 Discussion

Isaca Certified in Risk and Information Systems Control CRISC Question # 22 Topic 3 Discussion

CRISC Exam Topic 3 Question 22 Discussion:
Question #: 22
Topic #: 3

When developing a business continuity plan (BCP), it is MOST important to:


A.

identify an alternative location to host operations.


B.

identify a geographically dispersed disaster recovery site.


C.

prioritize critical services to be restored.


D.

develop a multi-channel communication plan.