Question #: 378
Topic #: 38

Which of the following is MOST important when conducting a post-implementation review as part of the system development life cycle (SDLC)?


A.

Verifying that project objectives are met


B.

Identifying project cost overruns


C.

Leveraging an independent review team


D.

Reviewing the project initiation risk matrix


Get Premium CRISC Questions