Isaca Certified in Risk and Information Systems Control CRISC Question # 281 Topic 29 Discussion
CRISC Exam Topic 29 Question 281 Discussion:
Question #: 281
Topic #: 29
A vendor ' s planned maintenance schedule will cause a critical application to temporarily lose failover capabilities. Of the following, who should approve this proposed schedule?
The business application owner is responsible for the operation and risk decisions related to the application. Since the loss of failover may impact business continuity, their approval is essential.
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit