Isaca Certified in Risk and Information Systems Control CRISC Question # 173 Topic 18 Discussion

Isaca Certified in Risk and Information Systems Control CRISC Question # 173 Topic 18 Discussion

CRISC Exam Topic 18 Question 173 Discussion:
Question #: 173
Topic #: 18

A key performance indicator (KPI) shows that a process is operating inefficiently, even though no control issues were noted during the most recent risk assessment. Which of the following should be done FIRST?


A.

Implement new controls.


B.

Recalibrate the key performance indicator (KPI).


C.

Redesign the process.


D.

Re-evaluate the existing control design.