Isaca Certified in Risk and Information Systems Control CRISC Question # 106 Topic 11 Discussion

Isaca Certified in Risk and Information Systems Control CRISC Question # 106 Topic 11 Discussion

CRISC Exam Topic 11 Question 106 Discussion:
Question #: 106
Topic #: 11

The BEST metric to monitor the risk associated with changes deployed to production is the percentage of:


A.

changes due to emergencies.


B.

changes that cause incidents.


C.

changes not requiring user acceptance testing.


D.

personnel that have rights to make changes in production.