Isaca Certified Information Systems Auditor CISA Question # 284 Topic 29 Discussion

Isaca Certified Information Systems Auditor CISA Question # 284 Topic 29 Discussion

CISA Exam Topic 29 Question 284 Discussion:
Question #: 284
Topic #: 29

Which of the following business continuity activities prioritizes the recovery of critical functions?


A.

Business continuity plan (BCP) testing


B.

Business impact analysis (BIA)


C.

Disaster recovery plan (DRP) testing


D.

Risk assessment