(You are tasked with assessing risks associated with a strategic initiative. A fellow business analysis professional suggests using a risk register. What is the purpose of a risk register?)


A.

To eliminate low-impact but probable risks


B.

To focus on highly impactful but improbable risks


C.

To prioritize risks based on their likelihood and impact


D.

To categorize risks randomly for fairness