The requirements life cycle continues beyond implementation and ends when the solution and the requirements that define it are retired. This marks the conclusion of the requirements ' relevance to the organization and their formal removal from active use.
Exact Extract from BABOK® Guide v3 – Section 5: Requirements Life Cycle Management Overview:
“The requirements life cycle ends when a solution component that a requirement traces to is retired.”