ECBA Exam Topic 1 Question 6 Discussion:
Question #: 6
Topic #: 1

When should prioritization of requirements take place?


A.

At the very beginning of an initiative only


B.

After the maintain requirements and trace requirements tasks have been completed


C.

Continually throughout the initiative


D.

After the maintain requirements task has been completed