Question #: 125
Topic #: 13

You are the business analyst for your organization and are preparing for the conduct elicitation activity. You'll need several stakeholders' roles as you prepare for this activity in your organization.

Which one of the following stakeholders may be responsible to dictate that a specific process or technique be

followed during your requirements elicitation activities?


A.

Project manager


B.

Regulator


C.

Functional management


D.

Project sponsor