Question #: 144
Topic #: 15

An organization has an agreement with a third-party vendor to have a fully operational facility, duplicate of the original site and configured to the organization's needs, in order to quickly recover operational

capability in the event of a disaster.

Which of the following best describes this approach to disaster recovery planning?


A.

Cold recovery plan.


B.

Outsourced recovery plan.


C.

Storage area network recovery plan.


D.

Hot recovery plan.