IIA Practice of Internal Auditing IIA-CIA-Part2 Question # 18 Topic 2 Discussion

IIA Practice of Internal Auditing IIA-CIA-Part2 Question # 18 Topic 2 Discussion

IIA-CIA-Part2 Exam Topic 2 Question 18 Discussion:
Question #: 18
Topic #: 2

The chief audit executive (CAE) of an organization has completed this year’s risk-based audit plan and realized that current staff resources are insufficient to meet the needs of the plan. What course of action should the CAE take?


A.

Amend the audit plan so that available audit resources are adequate to meet the plan’s requirements.


B.

Inform the board and senior management of the resources needed, as well as the associated risks.


C.

Communicate early to those unit managers whose areas would most likely not be able to get reviewed.


D.

Get approval from human resources regarding overtime payment to be made in an effort to complete the audit plan.


Get Premium IIA-CIA-Part2 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.