In the Work Order Tracking application, a Work Order is generated from a Preventive Maintenance (PM) record. How is the target finish date calculated?


A.

the Job Plan finish date


B.

the PM target finish date


C.

the Work Order target start date + the Job Plan duration


D.

the Job Plan start date + the Job Plan duration