IBM Maximo Manage v8.0 Implementation C1000-132 Question # 29 Topic 3 Discussion

IBM Maximo Manage v8.0 Implementation C1000-132 Question # 29 Topic 3 Discussion

C1000-132 Exam Topic 3 Question 29 Discussion:
Question #: 29
Topic #: 3

How can a Master Preventive Maintenance record be associated with multiple non-rotating assets?


A.

Use the Move/Modify Assets action.


B.

Use an Asset Template.


C.

Add the Assets to the Multiple Assets table on the Master Preventive Maintenance record.


D.

Use the Apply Down Hierarchy action on the Master Preventive Maintenance record.