GIAC Certified Project Manager Certification Practice Test GCPM Question # 49 Topic 5 Discussion

GIAC Certified Project Manager Certification Practice Test GCPM Question # 49 Topic 5 Discussion

GCPM Exam Topic 5 Question 49 Discussion:
Question #: 49
Topic #: 5

Sam is the project manager of a construction project in south Florida. This area of the United States is prone to hurricanes during certain parts of the year. As part of the project plan Sam and the project team acknowledge the possibility of hurricanes and the damage the hurricane could have on the project's deliverables, the schedule of the project, and the overall cost of the project. Once Sam and the project stakeholders acknowledge the risk of the hurricane they go on planning the project as if the risk is not likely to happen. What type of risk response is Sam using?


A.

Passive acceptance


B.

Mitigation


C.

Active acceptance


D.

Avoidance


Get Premium GCPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.