GIAC Certified Project Manager Certification Practice Test GCPM Question # 48 Topic 5 Discussion

GIAC Certified Project Manager Certification Practice Test GCPM Question # 48 Topic 5 Discussion

GCPM Exam Topic 5 Question 48 Discussion:
Question #: 48
Topic #: 5

You, with your team, are performing the work defined in the project management plan to achieve the project's objectives. In which of the following processes are you working on?


A.

Perform Quality Assurance


B.

Develop Project Team


C.

Manage Project Team


D.

Direct and Manage Project Execution


Get Premium GCPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.