GIAC Certified Project Manager Certification Practice Test GCPM Question # 26 Topic 3 Discussion

GIAC Certified Project Manager Certification Practice Test GCPM Question # 26 Topic 3 Discussion

GCPM Exam Topic 3 Question 26 Discussion:
Question #: 26
Topic #: 3

You work as a project manager for PassGuide Inc. You are working on a project that has a budget of $805,000 and you have completed 45 percent of the project work. Due to some errors, however, you have actually spent $430,000 of the budget. Management wants to know the project's cost performance index. Which of the following values will you report?


A.

0.87


B.

0.80


C.

0.84


D.

0.86


Get Premium GCPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.