GIAC Certified Project Manager Certification Practice Test GCPM Question # 25 Topic 3 Discussion

GIAC Certified Project Manager Certification Practice Test GCPM Question # 25 Topic 3 Discussion

GCPM Exam Topic 3 Question 25 Discussion:
Question #: 25
Topic #: 3

You work as a project manager for PassGuide Inc. You have to address the following information on the business case justifying the project, including return on investment. Which of the following documents will you use to address the above information?


A.

Project charter


B.

Risk register


C.

Stakeholder register


D.

Project scope statement