GAQM Professional in Project Management (PPM) PPM-001 Question # 54 Topic 6 Discussion

GAQM Professional in Project Management (PPM) PPM-001 Question # 54 Topic 6 Discussion

PPM-001 Exam Topic 6 Question 54 Discussion:
Question #: 54
Topic #: 6

Resource aggregation is…


A.

The process of assigning resources to each task


B.

The summation of all required resources during a set interval of time


C.

The process of examining the balance of required resources against actual resources over the duration of a project


D.

The process of assigning work to begin with