GAQM Associate in Project Management (APM) APM-001 Question # 67 Topic 7 Discussion

GAQM Associate in Project Management (APM) APM-001 Question # 67 Topic 7 Discussion

APM-001 Exam Topic 7 Question 67 Discussion:
Question #: 67
Topic #: 7

Which grid shows which resources are tied to work packages?


A.

Work breakdown structure (WBS)


B.

Responsibility assignment matrix (RAM)


C.

Project assignment chart


D.

Personnel assignment matrix


Get Premium APM-001 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.