GAQM Associate in Project Management (APM) APM-001 Question # 37 Topic 4 Discussion

GAQM Associate in Project Management (APM) APM-001 Question # 37 Topic 4 Discussion

APM-001 Exam Topic 4 Question 37 Discussion:
Question #: 37
Topic #: 4

The following is a network diagram for a project.

APM-001 Question 37

What is the critical path for the project?


A.

A-B-C-F-G-I


B.

A-B-C-F-H-I


C.

A-D-E-F-G-I


D.

A-D-E-F-H-I