GAQM Associate in Project Management (APM) APM-001 Question # 36 Topic 4 Discussion

GAQM Associate in Project Management (APM) APM-001 Question # 36 Topic 4 Discussion

APM-001 Exam Topic 4 Question 36 Discussion:
Question #: 36
Topic #: 4

The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as:


A.

Earned value management.


B.

Forecasting.


C.

Critical chain methodology.


D.

Critical path methodology.


Get Premium APM-001 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.