GAQM Associate in Project Management (APM) APM-001 Question # 210 Topic 22 Discussion

GAQM Associate in Project Management (APM) APM-001 Question # 210 Topic 22 Discussion

APM-001 Exam Topic 22 Question 210 Discussion:
Question #: 210
Topic #: 22

Perform Quality Control is accomplished by:


A.

Identifying quality standards that are relevant to the project and determining how to satisfy them.


B.

Monitoring and recording the results of executing the quality activities to assess performance and recommend necessary changes.


C.

Ensuring that the entire project team has been adequately trained in quality assurance processes.


D.

Applying Monte Carlo, sampling, Pareto analysis, and benchmarking techniques to ensure conformance to quality standards.