GAQM Associate in Project Management (APM) APM-001 Question # 203 Topic 21 Discussion

GAQM Associate in Project Management (APM) APM-001 Question # 203 Topic 21 Discussion

APM-001 Exam Topic 21 Question 203 Discussion:
Question #: 203
Topic #: 21

While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?


A.

Utilize the change control process.


B.

Crash the schedule to fix the defect.


C.

Leave the defect in and work around it.


D.

Fast-track the remaining development.