GAQM Associate in Project Management (APM) APM-001 Question # 197 Topic 20 Discussion

GAQM Associate in Project Management (APM) APM-001 Question # 197 Topic 20 Discussion

APM-001 Exam Topic 20 Question 197 Discussion:
Question #: 197
Topic #: 20

A measure of cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal and is expressed as the ratio of the cost needed for finishing the outstanding work to the remaining budget is known as the:


A.

budget at completion (BAC)


B.

earned value management (EVM)


C.

to-complete performance index


D.

cost performance index