GAQM Associate in Project Management (APM) APM-001 Question # 194 Topic 20 Discussion

GAQM Associate in Project Management (APM) APM-001 Question # 194 Topic 20 Discussion

APM-001 Exam Topic 20 Question 194 Discussion:
Question #: 194
Topic #: 20

When would resource leveling be applied to a schedule model?


A.

Before constraints have been identified


B.

Before it has been analyzed by the critical path method


C.

After it has been analyzed by the critical path method


D.

After critical activities have been removed from the critical path


Get Premium APM-001 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.