GAQM Associate in Project Management (APM) APM-001 Question # 184 Topic 19 Discussion

GAQM Associate in Project Management (APM) APM-001 Question # 184 Topic 19 Discussion

APM-001 Exam Topic 19 Question 184 Discussion:
Question #: 184
Topic #: 19

The product scope description is used to:


A.

Gain stakeholders' support for the project.


B.

Progressively elaborate the characteristics of the product, service, or result.


C.

Describe the project in great detail.


D.

Define the process and criteria for accepting a completed product, service, or result.