Exin Agile Scrum Foundation EX0-008 Question # 8 Topic 1 Discussion

Exin Agile Scrum Foundation EX0-008 Question # 8 Topic 1 Discussion

EX0-008 Exam Topic 1 Question 8 Discussion:
Question #: 8
Topic #: 1

Near the end of a Sprint, the team realizes that they will not be able to complete the stories they had committed to.

What is the best course of action for the team?


A.

Add resources and team members to meet the goals of the current Sprint.


B.

Ask the Product Owner to decide which stories can be delayed until the next Sprint.


C.

Decide on a new definition of 'done' for the Sprint Backlog Items.


Get Premium EX0-008 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.